November 2026

Lifting productivity in major infrastructure

Australia’s construction productivity is 7% lower than in 1990. A new report from CEDA and WSP finds poor risk management, fragmented procurement and bespoke infrastructure are holding us back.

Building what Australia needs: lifting productivity in major infrastructure was developed by the Committee for Economic Development of Australia (CEDA) and WSP following a series of roundtables with senior leaders across the water, energy, resources and public infrastructure sectors.

“Australia doesn’t have an infrastructure ambition problem,” says Greg Kane, President and Managing Director for WSP in Australia. “The challenge is creating the conditions to deliver it productively and efficiently.”

The report offers some striking examples of productivity barriers in the infrastructure sector:

  • Procurement complexity: The Queensland Government’s construction procurement framework spans more than 15 documents and 1,000 pages.
  • Declining government capability: Just 14% of Australia’s engineers work in the public sector, limiting governments’ capacity to act as informed infrastructure clients.
  • Poorly understood risks: Infrastructure Australia research found only 25% of respondents believed critical risks were well understood during project planning.
  • Premature project commitments: While only a third of megaprojects are announced prematurely, they account for more than three-quarters of total cost overruns.
  • Costly changes: WSP compared two otherwise similar projects and found that change notices increased from 66 in 2004 to 320 in 2020.

“Right now, governments are paying contractors a premium to carry risks they can’t absorb, and then paying again when those risks land,” says CEDA economist and the report’s co-author, Jonathon Mahon. “That cycle is draining resources from delivery and leaving industry without the margin or certainty to invest in better ways of building.”

The report identifies 10 priorities for reform, including better upfront project definition, fairer allocation of risk, simpler and more consistent procurement processes, and greater investment in government engineering and commercial capability.

It also makes the case for treating infrastructure less as a series of one-off projects and more as a sustained program of work, allowing engineering firms and contractors to invest in digital tools, standardised designs and modern methods of construction.

Victoria’s Level Crossing Removal Project demonstrates the potential. By packaging similar projects together and encouraging standardisation, the program delivered 85 crossing removals ahead of schedule, with the average cost per crossing falling from $191.8 million to $180 million.

“Major projects today are being delivered in an increasingly complex environment, with more requirements, interfaces and competing objectives to manage,” WSP’s Greg Kane adds.

“Simply pushing industry harder isn’t the answer. We need to simplify where we can, create greater certainty earlier and be clearer about the trade-offs we’re willing to make. If we get those settings right, we give industry a better chance to invest, innovate and ultimately deliver more from the capital and capability Australia has available.”

 

Download Building what Australia needs: lifting productivity in major infrastructure.

 